Homefab has been prepping the new site for Stage 1 of our new Homefab Factory. From vacant overgrown land, the block is now ready for building to commence in July 2019.

Scott Broadley Builder
Firecraft Environmental

With the tireless efforts of our Builder -Scott Broadley, along with Firecraft Environmental (who have been with us for Project Management, site preparation and safety consultation, earthworks & landscaping) as well as our dedicated production staff who have assisted from the start, we have:

Cleaned and prepared the block... Built and reinforced rear retainer wall...

Cleaned and prepared the block…
Built and reinforced rear retainer wall…

Built new fences...

Built new fences…

Demolished the old mezzanine floor…

Demolished brick walls...

Demolished brick walls…

A more open and easily accessible factory...

To make way for a more open and easily accessible factory…

New plumbing and stormwater...

Diamond saw concrete slabs to make way for the new plumbing and stormwater…

Landscaping for fence lines...

Firecraft & production staff began landscaping for fence lines…

Completed Earthworks with 2,215 tonnes of fill...

Completed Earthworks with 2,215 tonnes of fill…

View of the new pad ready for slab pour.

To create the new pad ready for slab pour…

The new slab through RTS Concreting will be poured in November 2019.

Stay tuned…